RAISING BOLIVAR
Crews working on
a $6.16 million road project funded by a federal economic stimulus program will
begin raising Bolivar Peninsula’s only highway, which was damaged by Hurricane
Ike. Work is scheduled to start today.
A second project, already under way, should help protect
the lowest-lying parts of the highway from five-year floods, Bill Babbington,
an engineer with the Texas Department of Transportation, said.
Crews will begin installing culverts and pipes on state
Highway 87 between the Galveston-Bolivar Ferry and state state Highway 124 with
the intent of raising the road from 3 inches to 21/2 feet, Babbington said. Not
all of the highway must be elevated.
Crews will not shut down the road but will have flagmen
to direct single-lane traffic on the two-lane highway. The project is expected
to conclude at year’s end, weather permitting, Babbington said.
State contractors are installing concrete barriers along
the lowest-lying stretches of the highway, which extends some 30 miles along
the peninsula.
Contractors are burying two concrete, triangular
barriers side by side in the sand between the road and the beach.
They will then place a third barrier atop the two, reaching
a height of 1 foot above the road, Babbington said.
The lowest section near the state Highway 124 junction
is just 41/2 feet above sea level.
“The intent is to prevent some high tides and minor
tropical storms from inundating that road,” Babbington said.
“That happens during spring tides, where they get water
on Highway 87.”
The barriers won’t be continuously connected, Babbington
said.
“It runs from Highway 124 to Rollover Pass in segments,”
Babbington said.
“We tried to address the areas that lost most of the
beach.”
The state isn’t installing barriers where significant
beach remains, Babbington said.
The $513,868 barrier project began June 8 and is
expected to be completed in 45 days, weather permitting, Babbington said.
Read full story at Galveston County Daily News
Metal Utility Poles Built to Withstand Hurricane
When the next
hurricane blows through Galveston County, Entergy Corp. officials believe their
new metal utility poles could help restore electricity sooner to residents of
the Bolivar Peninsula.
The $15 million project to erect and wire 201 massive
poles could be complete by Aug. 28, said Elaine Dearbonne, the company’s
capital projects manager for Texas.
The 18 miles of transmission lines would stretch between
substations in Chambers and Galveston counties, ending at the Himex substation
at High Island.
When Hurricane Ike made landfall Sept. 13, it caused
extensive flooding and damaged hundreds of wooden utility poles that littered
the landscape along state highways 124 and 87 on the peninsula. Some residents
were without power for about two months.
The first line leading to High Island wasn’t charged
until Oct. 3, said Larry Daspit, a spokesman for Entergy.
“We’re rebuilding with steel poles to withstand a
140-mph storm,” Dearbonne said. The company adopted the standard close to the
coast.
The transmission lines, which rest on poles that are as
thick as 5 feet in diameter and stand between 85 to 150 feet high, carry 69,000
volts or more and cannot be used as distribution lines without reducing
electrical output. Once the output is reduced at a substation, it is then sent
along distribution lines capable of carrying 34,500 volts to transformers that
power homes.
If the metal structures withstand the next storm, the
company will spend less time erecting new poles. The goal is to reduce the time
residents are without power, Dearbonne said.
Every pole was engineered for the soil where contractors
are sinking them, some to depths of 20 feet or more, depending on the geology,
said Dean Adams, the company’s construction supervisor for Texas and the
Southwest.
After the poles are installed, they will be strung, 2
miles at a time, with aluminum-conductor, steel-reinforced lines, said Amy
Hensarling, a construction engineer with Entergy.
Galveston County Commissioner Patrick Doyle said most of
the peninsula had power restored within two months after Ike’s landfall.
“It will definitely help on the next go-round,” Doyle
said. “Even during tropical storms, a lot of times we lose power on High
Island.”
Burying the lines would be too pricey, Doyle said.
Once the company completes the transmission-line
project, customers should not notice the switch, Adams said.
By
Chris Paschenko The Daily News